They were doing some activity that shook the whole house. Looks like they were chipping away at the area where the new slab is going to join the old slab (i.e. existing house). See that piece of blue tape? There used to be a few more inches of concrete beyond that.
They also removed a bit more of the driveway.
I have been waiting for them to do that for a while. I was told that the part of the slab that joins the driveway, the house, the patio and the pavers in the back is not going to be poured until much later. That is not my fridge nor my microwave. These guys know how to travel.
Not much difference on the next part. More rebar and some posts to which they can fasten the framing for the interior walls.
I just bumped into the project supervisor literally minutes ago and he said they will be pouring tomorrow. That'll make for some really dramatic pictures. I'll bet you can't wait!